A study of the critical chain project management method applied to a multiproject system
Robert Eduardo Cooper Ordonez, Mario Vanhoucke, Jose Coelho, Rosley Anholon, Olivio Novaski
ARTIGO
Inglês
In 1997, Eliyahu Goldratt proposed a method called critical chain project management (CCPM) to minimize the inefficiencies identified in traditional project management. The project management community accepted the proposed method as a viable alternative. However, to allow its implementation with a...
In 1997, Eliyahu Goldratt proposed a method called critical chain project management (CCPM) to minimize the inefficiencies identified in traditional project management. The project management community accepted the proposed method as a viable alternative. However, to allow its implementation with a multiproject system, more research was necessary. Seeking to identify the key factors that influence the performance of the multiproject system applying the CCPM method, we performed a case study. Logistic regression analysis showed that applying the CCPM method in a multiproject system allows for better time estimation of activities and facilitates the allocation of critical resources
FUNDAÇÃO DE AMPARO À PESQUISA DO ESTADO DE SÃO PAULO - FAPESP
Fechado
A study of the critical chain project management method applied to a multiproject system
Robert Eduardo Cooper Ordonez, Mario Vanhoucke, Jose Coelho, Rosley Anholon, Olivio Novaski
A study of the critical chain project management method applied to a multiproject system
Robert Eduardo Cooper Ordonez, Mario Vanhoucke, Jose Coelho, Rosley Anholon, Olivio Novaski
Fontes
Project management journal Vol. 50, no. 3 (Mar., 2019), p. 322-354 |